[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141080":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141080,799,1,"单选题","施工成本分析是在（ ）的基础上，对成本的形成过程和影响因素进行分析。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工成本计划",false,{"key":16,"text":17,"correct":14},"B","施工成本预测",{"key":19,"text":20,"correct":21},"C","施工成本核算",true,{"key":23,"text":24,"correct":14},"D","施工成本考核","本题考核的是施工成本分析。 施工成本分析是在施工成本核算的基础上，对成本的形成过程和影响成本升降的因素进行分析，以寻求进一步降低成本的途径，包括有利偏差的挖掘和不利偏差的纠正。施工项目成本核算所提供的各种成本信息是成本预测、成本计划、成本控制、成本分析和成本考核等各个环节的依据。 综上所述，正确选项为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]