[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141058":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141058,799,1,"单选题","（2020年真题）某混凝上工程施工情况如下图，清单综合单价为1000元\u002Fm3，按月结算，根据赢得值法，该工程6月末进度偏差(SV)是（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","-215",true,{"key":16,"text":17,"correct":18},"B","-200",false,{"key":20,"text":21,"correct":18},"C","-125",{"key":23,"text":24,"correct":18},"D","-60","P88-100 六月末的SV=BCWP-BCWS=【（2300*4+2500*2+1250）-（2500*4+2600*2+1200×2）】×1000=-2150000=-215万",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]