[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141057":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141057,799,1,"单选题","（2020年真题）某工程第三个月末时的已完工作实际费用(ACWP)为1200万元、已完工作预算费用(BCWP)为1000万元、计划工作预算费用(BCWS)为1500万元，根据赢得值法判断分析应采取的措施是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","迅速增加人员投入",false,{"key":16,"text":17,"correct":18},"B","增加高效人员投入",true,{"key":20,"text":21,"correct":14},"C","抽出部分人员，增加少量骨干人员",{"key":23,"text":24,"correct":14},"D","用工作效率高的人员更换一批工作效率低的人员","P88-100",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]