[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141053":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141053,799,1,"单选题","下图所示为拟完工程和已完工程计划施工成本的比较，图中△表示t时刻的（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工成本节约值",false,{"key":16,"text":17,"correct":14},"B","施工成本增加值",{"key":19,"text":20,"correct":21},"C","施工进度滞后量",true,{"key":23,"text":24,"correct":14},"D","施工进度提前量","@##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]