[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141052":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141052,799,1,"单选题","某建设工程项目施工过程中，收集到的分部工程A的资料见下表。分部工程A的施工成本节约（ ）元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","35000",false,{"key":16,"text":17,"correct":14},"B","32000",{"key":19,"text":20,"correct":14},"C","18000",{"key":22,"text":23,"correct":24},"D","15000",true,"本题考核的是施工成本偏差。 施工成本偏差=已完工程实际施工成本-已完工程计划施工成本=已完工程量×实际单位成本-已完工程量×计划单位成本=（500×320-500×350）元=-15000元。因计算结果为负数，则表示施工成本节约15000元。 综上所述，正确选项为D。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]