[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141051":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141051,799,2,"多选题","某混凝土工程的清单综合单价1000元\u002Fm3，按月结算，进度数据如下表。按赢得值法计算，3月末已完工作实际费用（ACWP）是9790千元。该工程3月末参数或指标正确的有（）。2018真题",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","已完工作预算费用（BCWP）是9100千元",true,{"key":16,"text":17,"correct":14},"B","进度偏差（SV）是－1600千元",{"key":19,"text":20,"correct":14},"C","费用绩效指数（CPI）是0.93",{"key":22,"text":23,"correct":14},"D","计划工作预算费用（BCWS）是10700千元",{"key":25,"text":26,"correct":27},"E","费用偏差（CV）是690千元",false,"ABCD","本题考查的是赢得值（挣值）法。本题中三月末的指标为：BCWP＝1000×（4500＋2300×2）＝9100千元，BCWS＝1000×（4500＋2500×2＋1200）＝10700千元，SV＝BCWP－BCWS＝9100－10700＝－1600千元，CV＝BCWP－ACWP＝－690千元，CPI＝BCWP\u002FACWP＝0.93。综上，只有选项E错误。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]