[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141050":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141050,799,1,"单选题","某项目地面铺贴的清单工程量为1000m2，预算费用单价60元\u002Fm2，计划每天施工100m2。2018真题第6天检查时发现，实际完成800m2，实际费用为5万元。2018真题根据上述情况，预计项目完工时的费用偏差（ACV）是（）元。2018真题",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2500",false,{"key":16,"text":17,"correct":14},"B","2000",{"key":19,"text":20,"correct":21},"C","－2500",true,{"key":23,"text":24,"correct":14},"D","－2000","本题考查的是偏差分析的表达方法。项目完工的工程量为1000㎡，第6天检查时实际完成800㎡，实际费用为5万元，则实际费用单价＝50000÷800＝62.5元\u002F㎡，那么项目完工时的费用偏差ACV＝已完工作预算费用－已完工作实际费用＝1000×60－1000×62.5＝－2500（元）。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]