[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141047":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141047,799,1,"单选题","某工程项目的赢得值曲线如下图，关于项目偏差原因分析与纠偏措施的说法，正确的是（ ）。2017",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","效率高，进度较慢，投入延后",false,{"key":16,"text":17,"correct":14},"B","效率较高,进度较慢，投入超前",{"key":19,"text":20,"correct":21},"C","抽出部分人员，放慢进度",true,{"key":23,"text":24,"correct":14},"D","增加人员投入，加快速度","本题考查的是赢得值。图示中BCWP＞ACWP＞BCWS，SV＞0，CV＞0，表示效率较高，进度较快，投入延后，要采取措施抽出部分人员，放慢进度。参见教材10。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]