[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141045":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141045,799,1,"单选题","应用曲线法进行施工成本偏差分析时，已完工作实际成本曲线与已完工作预算成本曲线的竖向距离表示项目进展的（ ）。 2016",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","进度累计偏差",false,{"key":16,"text":17,"correct":14},"B","进度局部偏差",{"key":19,"text":20,"correct":21},"C","成本累计偏差",true,{"key":23,"text":24,"correct":14},"D","成本局部偏差","本题考查的是偏差分析的表达方法。CV=BCWP-ACWP，由于两项工作均以已完工作为计算基数，所以两者之差反映的是项目进展的费用偏差。累计成本偏差是指已完工程在某一时间点上实际总成本与相应的计划总成本的差异。在曲线法中，检测的某一时间点上两者的竖向差值体现为成本累计偏差。参见教材04。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]