[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141044":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141044,799,1,"单选题","某分项工程某月计划工程量为3200m2，计划单价为15元\u002Fm2；月底核定承包商实际完成工程量为2800m2，实际单价为20元\u002Fm2，则该工程的已完成工作实际费用（ACWP）为（ ）元。 2016",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","56000",true,{"key":16,"text":17,"correct":18},"B","42000",false,{"key":20,"text":21,"correct":18},"C","48000",{"key":23,"text":24,"correct":18},"D","64000","本题考查的是赢得值法。WS=3200，BC=15，WP=2800，AC=20，所以，ACWP=20×2800=56000元。参见教材01～102。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]