[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141041":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141041,799,2,"多选题","某工作横道图费用偏差分析如下图，正确的有（ ）。( 2015真题 )",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","费用超支",true,{"key":16,"text":17,"correct":14},"B","进度较快",{"key":19,"text":20,"correct":21},"C","效率较高",false,{"key":23,"text":24,"correct":21},"D","可采用抽出部分人员，放慢进度的措施",{"key":26,"text":27,"correct":14},"E","投入超前","ABE","本题考查的是偏差原因分析与纠偏措施。本题中BCWP大于BCWS，表明较快；BCWP小于ACWP，说明费用超支；又因为ACWP>BCWP>BCWS，所以效率较低，投入超前，应抽出部分人员，增加少量骨干人员。参见教材11。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]