[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141031":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141031,799,1,"单选题","应用曲线法进行施工成本偏差分析时，已完工作实际成本曲线与已完工作预算成本曲线的竖向距离，表示（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本偏差",true,{"key":16,"text":17,"correct":18},"B","进度偏差",false,{"key":20,"text":21,"correct":18},"C","进度局部偏差",{"key":23,"text":24,"correct":18},"D","成本局部偏差","本题主要考查施工成本分析的曲线法。 图中费用偏差CV=已完工作预算费用（BCWP）－已完工作实际费用（ACWP），反映项目进展的费用偏差；进度偏差SV=已完工作预算费用（BCWP）－计划工作预算费用（BCWS），反映项目进展的进度偏差。题目中已完工作实际成本曲线与已完工作预算成本曲线的竖向距离即CV，表示已完工作实际成本与预算成本的偏差，即成本偏差。 综上所述，本题正确选项为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]