[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141028":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141028,799,1,"单选题","偏差分析的方法不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","横道图法",false,{"key":16,"text":17,"correct":14},"B","表格法",{"key":19,"text":20,"correct":14},"C","曲线法",{"key":22,"text":23,"correct":24},"D","比较法",true,"本题主要考查施工成本偏差分析的表达方法。 D项：比较法是施工成本分析的基本方法，而不是成本偏差分析的表达方法。故D项错误。 ABC项：施工成本偏差分析常用的表达方法有：横道图法、表格法和曲线法。故ABC都属于偏差分析的方法，故ABC项说法正确。 本题是选非题，综上所述，本题正确选项为D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]