[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141026":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141026,799,1,"单选题","某工程10月份拟完工程计划施工成本50万元，已完工程计划施工成本45万元，已完工程实际施工成本48万元，该工程10月底施工成本偏差和进度偏差分别是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本超支3万元，进度拖延5万元",true,{"key":16,"text":17,"correct":18},"B","成本超支3万元，进度拖延3万元",false,{"key":20,"text":21,"correct":18},"C","成本节约2万元，进度提前5万元",{"key":23,"text":24,"correct":18},"D","成本节约2万元，进度提前3万元","本题考核的是赢得值法。计算公式为： 费用偏差CV=已完工作预算费用BCWP－已完工作实际费用ACWP 进度偏差SV=已完工作预算费用BCWP－计划工作预算费用BCWS 本题中： 费用偏差CV=已完工作预算费用BCWP－已完工作实际费用ACWP=45－48=－3万元，即成本超支3万元 进度偏差SV=已完工作预算费用BCWP－计划工作预算费用BCWS=45－50=－5万元 ，即进度拖延5万元 综上所述，本题正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]