[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141025":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141025,799,1,"单选题","应用S形曲线法进行施工成本偏差分析时，已完工作实际成本曲线与已完工作预算成本曲线的竖向距离表示施工（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度累计偏差",false,{"key":16,"text":17,"correct":18},"B","成本累计偏差",true,{"key":20,"text":21,"correct":14},"C","进度局部偏差",{"key":23,"text":24,"correct":14},"D","成本局部偏差","本题考核的是S型曲线法。 应用S型曲线法进行施工成本偏差分析时，已完工作实际成本曲线与已完工作预算成本曲线的竖向距离表示施工成本累计偏差。曲线法中有三个参数，为计划工作预算费用（BCWS）、已完工作预算费用（BCWP）、已完工作实际费用（ACWP）曲线。 SV=BCWP-BCWS，反映的是项目进展的进度偏差； CV=BCWP-ACWP，反映的是项目进展的费用偏差。 综上所述，正确选项为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]