[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141019":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141019,799,1,"单选题","某分项工程计划工程量3000ｍ3，计划成本15元\u002Fｍ3，实际完成工程量2500ｍ3，实际成本20元\u002Fｍ3，则该分项工程的施工进度偏差为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拖后7500元",true,{"key":16,"text":17,"correct":18},"B","提前7500元",false,{"key":20,"text":21,"correct":18},"C","拖后12500元",{"key":23,"text":24,"correct":18},"D","提前12500元","本题主要考查施工进度偏差。 进度偏差（SV）=已完工作预算费用（BCWP）－计划工作预算费用（BCWS）=2500×15－3000×15=－7500元，即实际进度落后于计划进度7500元。 综上所述，本题正确选项为B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]