[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141016":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141016,799,1,"单选题","某施工企业进行土方开挖工程，按合同约定3 月份的计划工作量为2400m3,计划单价是12 元\u002Fm3；到月底检查时，确认承包商完成的工程量为2000m3，实际单价为15 元\u002Fm3。则该工程的进度偏差（SV）和进度绩效指数(SPI)分别为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.6 万元；0.80",false,{"key":16,"text":17,"correct":14},"B","-0.6 万元；0.83",{"key":19,"text":20,"correct":21},"C","-0.48 万元；0.83",true,{"key":23,"text":24,"correct":14},"D","0.48 万元；0.80","本题考核的是赢得值法。 已完工作预算费用(BCWP)=已完成工作量×预算（计划）单价=2000m3×12元\u002Fm3=2.4万元， 计划工作预算费用(BCWS)=计划工作量×预算（计划）单价=2400m3×12元\u002Fm3=2.88万元， 进度偏差(SV)=已完工作预算费用(BCWP)-计划工作预算费用(BCWS)=2.4-2.88 =-0.48万元， 进度绩效指数SPI=已完工作预算费用（BCWP）／计划工作预算费用（BCWS）= 2.4\u002F2.88=0.83。 综上所述，本题正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]