[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141015":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141015,799,1,"单选题","某工程主体结构混凝土工程为3200m3，预算单价为550元\u002Fm3，计划4个月内均衡完成。开工后，混凝土实际采购价格为560\u002Fm3。施工至第二个月月底，实际累计完成混凝土工程量为1800m3，则此时的进度偏差为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","11.8",false,{"key":16,"text":17,"correct":14},"B","11.2",{"key":19,"text":20,"correct":21},"C","11.0",true,{"key":23,"text":24,"correct":14},"D","-1.8","本题考核的是进度偏差计算。 进度偏差=已完工作预算费用-计划工作预算费用，其中，已完工作预算费用=已完工作量×预算单价，计划工作预算费用=计划工作量×预算单价。本题中，进度偏差=1800×550-3200\u002F4×2×550=110000（元）。 综上所述，正确选项为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]