[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141001":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141001,799,1,"单选题","建设工程项目施工成本控制涉及的时间范围是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","从设计准备开始至项目竣工验收时止",false,{"key":16,"text":17,"correct":14},"B","从设计阶段开始至项目动用时止",{"key":19,"text":20,"correct":21},"C","从工程投标报价开始至项目竣工结算完成为止",true,{"key":23,"text":24,"correct":14},"D","从项目开工时开始至项目竣工结算完成为止","本题主要考查建设工程项目施工成本控制。 建设工程项目施工成本控制应从工程投标报价开始，直至项目竣工结算完成为止，贯穿于项目实施的全过程。 综上所述，本题正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]