[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141000":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141000,799,1,"单选题","项目成本指标控制的工作包括：①采集成本数据，监测成本形成过程；②制定对策，纠正偏差；③找出偏差，分析原因；④确定成本管理分层次目标。其正确的工作程序是（）。2018真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","④→①→③→②",true,{"key":16,"text":17,"correct":18},"B","①→②→③→④",false,{"key":20,"text":21,"correct":18},"C","①→③→②→④",{"key":23,"text":24,"correct":18},"D","②→④→③→①","本题考查的是成本控制的依据和程序。项目成本指标控制程序如下：（1）确定成本管理分层次目标；（2）采集成本数据，检测成本形成过程；（3）找出偏差分析原因；（4）制定对策，纠正偏差；（5）调整改进成本管理方法。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]