[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140997":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140997,799,2,"多选题","工程项目施工成本控制的依据有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程造价",false,{"key":16,"text":17,"correct":18},"B","施工组织设计",true,{"key":20,"text":21,"correct":18},"C","工程承包合同",{"key":23,"text":24,"correct":18},"D","进度报告",{"key":26,"text":27,"correct":18},"E","工程变更","BCDE","本题主要考查施工成本控制的依据。 施工成本控制的依据包括以下内容：工程承包合同；施工成本计划；进度报告；工程变更；施工组织设计；分包合同等。 综上所述，本题正确选项为BCDE项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]