[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140995":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1140995,799,1,"单选题","施工成本计划是施工项目成本控制的一个重要环节。一般情况下，施工成本计划总额应控制在（ ）的范围内。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","固定成本",false,{"key":16,"text":17,"correct":18},"B","目标成本",true,{"key":20,"text":21,"correct":14},"C","预算成本",{"key":23,"text":24,"correct":14},"D","实际成本","本题主要考查施工项目成本控制。 施工成本计划的编制以成本预测为基础，关键是确定目标成本。一般般情况下，施工成本计划总额应控制在目标成本的范围内，并使成本计划建立在切实可行的基础上。 综上，本题正确答案应为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]