[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140993":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140993,799,2,"多选题","施工总成本目标确定之后，还需通过编制详细的实施性施工成本计划把目标成本层层分解，落实到施工过程的每个环节，有效地进行成本控制，施工成本计划的编制方式有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","按施工成本组成",true,{"key":16,"text":17,"correct":14},"B","按工程进度",{"key":19,"text":20,"correct":21},"C","按工程适用范围",false,{"key":23,"text":24,"correct":21},"D","按项目内容",{"key":26,"text":27,"correct":14},"E","按项目组成","ABE","本题主要考查对施工成本计划的理解。 施工成本计划的编制方式有按施工成本组成编制施工成本计划、按项目组成编制施工成本计划和按工程进度编制施工成本计划。 综上所述，本题正确答案为ABE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]