[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140991":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140991,799,1,"单选题","对大中型工程项目，按项目组成编制施工成本计划时，其总成本分解的顺序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单项工程成本→单位（子单位）工程成本→分部（子分部）工程成本→分项工程成本",true,{"key":16,"text":17,"correct":18},"B","单位（子单位）工程成本→单项工程成本→分部（子）分部→工程成本→分项工程成本",false,{"key":20,"text":21,"correct":18},"C","分项工程成本→分部（子分部）工程成本→单位（子单位）工程成本→单项工程成本",{"key":23,"text":24,"correct":18},"D","分部（子分部）工程成本→分项工程成本→单项工程成本→单位（子单位）工程成本","本题主要考查大中型工程项目的组成。 大中型的工程项目通常是由若干单项工程构成的，而每个单项工程包括了多个单位工程，每个单位工程又是由若干个分部分项工程构成的。 综上，本题正确答案应为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]