[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140989":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140989,799,1,"单选题","在编制成本支出计划时，要在项目的总的方面考虑总的预备费，也要在（ ）中安排适当的不可预见费。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","所有的分项工程中",false,{"key":16,"text":17,"correct":14},"B","所有的检验批中",{"key":19,"text":20,"correct":14},"C","主要的检验批中",{"key":22,"text":23,"correct":24},"D","主要的分项工程中",true,"本题主要考查按项目组成编制施工成本计划的方法。 在编制成本支出计划时，要在项目总的方面考虑总的预备费，也要在主要的分项工程中安排适当的不可预见费，避免在具体编制成本计划时，可能发现个别单位工程或工程量表中某项内容的工程量计算有较大出入，使原来的成本预算失实，并在项目实施过程中对其尽可能地采取一些措施。 综上所述，本题正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]