[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140985":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1140985,799,1,"单选题","某项目按施工进度编制的施工成本计划入下图，则4月份计划成本是（ ）万元。( 2015真题 )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","300",false,{"key":16,"text":17,"correct":18},"B","400",true,{"key":20,"text":21,"correct":14},"C","750",{"key":23,"text":24,"correct":14},"D","1150","本题考查的是按施工进度编制施工成本计划的方法。根据时间－成本累积曲线，可以推导出每月的进度计划成本，1150-750=400万元。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]