[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140984":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1140984,799,1,"单选题","某项目施工成本计划如下图，则5月末计划累积成本支出为（）万元。2018真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","325",false,{"key":16,"text":17,"correct":18},"B","270",true,{"key":20,"text":21,"correct":14},"C","180",{"key":23,"text":24,"correct":14},"D","75","本题考查的是按工程实施阶段编制成本计划的方法。第1月末计划累积成本支出是10万元；第2月末计划累积成本支出是10＋（10＋20）＝40万元；第3月末计划累积成本支出是40＋（10＋20＋15＋30）＝115万元；第4月末计划累积成本支出是115＋（20＋15＋30）＝180万元；第5月末计划累积成本支出是180＋（20＋15＋30＋25）＝270万元。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]