[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140979":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140979,799,1,"单选题","已知某施工项目的计划数据资料如下表所示，则第3周的施工成本计划值是（ ）万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","30",false,{"key":16,"text":17,"correct":14},"B","60",{"key":19,"text":20,"correct":14},"C","75",{"key":22,"text":23,"correct":24},"D","90",true,"本题考核的是施工成本计划值的计算。 第3周的工作包括土方开挖、混凝土垫层及混凝土基础，其施工成本计划值=15+15+60=90（万元）。 综上所述，正确选项为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]