[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140976":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140976,799,2,"多选题","按最早开始时间编制的施工计划及各工作每月成本强度（单位：万元\u002F月）如下图，D工作可以按最早开始时间或最迟开始时间进行安排。则4月份的施工成本计划值可以是（ ）万元。( 2015真题 )",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","60",false,{"key":16,"text":17,"correct":18},"B","50",true,{"key":20,"text":21,"correct":18},"C","25",{"key":23,"text":24,"correct":14},"D","15",{"key":26,"text":27,"correct":14},"E","10","BC","本题考查的是双代号时标网络图及施工成本计划。因为D工作可以按最早开始时间或最迟开始时间进行安排，所以4月份可以是只干E和C工作，施工计划值为15+10=25万元；或者D按最早开始时间安排，4月份工作C、D、E三项工作，施工计划值为15+10+25=50万元。@##",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]