[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140975":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140975,799,1,"单选题","施工成本计划的编制以成本预测为基础，关键是确定（ ）。2014",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","目标成本",true,{"key":16,"text":17,"correct":18},"B","预算成本",false,{"key":20,"text":21,"correct":18},"C","固定成本",{"key":23,"text":24,"correct":18},"D","实际成本","本题考查的是按施工成本组成编制施工成本计划的方法。施工成本计划的编制以成本预测为基础，关键是确定目标成本。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]