[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140968":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140968,799,2,"多选题","建设工程项目施工成本计划应在（ ）的前提下进行编制。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目施工组织设计完成",false,{"key":16,"text":17,"correct":18},"B","项目实施方案不断优化",true,{"key":20,"text":21,"correct":18},"C","项目实施方案确定",{"key":23,"text":24,"correct":14},"D","组织管理措施确定",{"key":26,"text":27,"correct":14},"E","项目质量目标确定","BC","本题主要考查施工成本计划。 项目施工成本计划工作主要是在项目经理负责下，在项目实施方案确定和不断优化的前提下进行编制，因为编制中的关键前提---确定目标成本，这是成本计划的核心，不同的实施方案将导致直接工程费、措施费和企业管理费的差异。所以项目施工成本计划工作应在项目实施方案确定和不断优化的前提下进行编制。 综上所述，本题正确答案为BC。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]