[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140965":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1140965,799,1,"单选题","按建设项目工程成本构成编制施工成本计划时，将施工成本分解为（ ）等。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直接费、间接费、利润、税金",false,{"key":16,"text":17,"correct":18},"B","人工费、材料费、施工机械使用费、措施项目费、企业管理费",true,{"key":20,"text":21,"correct":14},"C","单位工程施工成本及分部、分项工程施工成本",{"key":23,"text":24,"correct":14},"D","分部分项工程费、其他项目费、规费","本题主要考查施工成本计划的具体内容。 包括 编制说明 施工成本计划指标 按工程量清单列出的单位工程计划成本汇总表 按成本性质划分的单位工程成本汇总表。其中第四项按成本性质划分将施工成本分为人工费、材料费、机械费、措施费、企业管理费和税费。 综上所述，本题正确选项为B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]