[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140962":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140962,799,1,"单选题","施工成本计划的编制以成本预测为基础，关键是确定（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","目标成本",true,{"key":16,"text":17,"correct":18},"B","预算成本",false,{"key":20,"text":21,"correct":18},"C","计划成本",{"key":23,"text":24,"correct":18},"D","实际成本","本题主要考查的是施工成本计划的编制依据。 施工成本计划的编制以成本预测为基础，关键是确定目标成本。一般情况下，施工成本计划总额应控制在目标成本的范围内，并使成本计划建立在切实可行的基础上。 综上所述，正确选项为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]