[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140961":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1140961,799,1,"单选题","编制施工项目成本计划，关键是确定项目的（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","概算成本",false,{"key":16,"text":17,"correct":14},"B","成本构成",{"key":19,"text":20,"correct":21},"C","目标成本",true,{"key":23,"text":24,"correct":14},"D","实际成本","本题考查的是按施工成本组成编制施工成本计划的方法的内容。 施工项目成本计划的编制以成本预测为基础，关键是确定目标成本。 综上所述，本题正确选项为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]