[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140950":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140950,799,1,"单选题","编制施工项目成本计划的关键是确定（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","目标成本",true,{"key":16,"text":17,"correct":18},"B","预算成本",false,{"key":20,"text":21,"correct":18},"C","平均成本",{"key":23,"text":24,"correct":18},"D","实际成本","本题主要考查施工项目成本计划的编制。 施工成本计划是施工项目成本控制的一个重要环节，施工成本计划的编制以成本预测为基础，关键是确定目标成本。结合施工组织设计的编制过程，通过不断优化施工技术方案和合理配置生产要素，进行工、料、机消耗的分析，制订一系列节约成本和挖潜措施，确定施工成本计划。 综上所述，本题正确选项为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]