[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140946":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1140946,799,1,"单选题","实施性成本计划是在项目施工准备阶段，采用（ ）编制的施工成本计划。2014",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","估算指标",false,{"key":16,"text":17,"correct":14},"B","概算定额",{"key":19,"text":20,"correct":21},"C","施工定额",true,{"key":23,"text":24,"correct":14},"D","预算定额","本题考查的是实施性成本计划。实施性成本计划是项目施工准备阶段的施工预算成本计划，它是以项目实施方案为依据，以落实项目经理责任目标为出发点，采用企业的施工定额通过施工预算的编制而形成的实施性施工成本计划。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]