[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140935":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1140935,799,1,"单选题","在施工成本计划中，（ ）施工成本计划是项目施工准备阶段的施工预算成本计划，是以项目实施方案为依据，落实项目经理责任目标为出发点，采用企业的施工定额通过施工预算的编制而形成的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","控制性",false,{"key":16,"text":17,"correct":14},"B","竞争性",{"key":19,"text":20,"correct":21},"C","实施性",true,{"key":23,"text":24,"correct":14},"D","项目性","本题主要考查成本计划的类型。 施工成本计划按其作用可分为三类，如图所示： 综上所述，本题正确选项为C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]