[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140934":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1140934,799,1,"单选题","按照企业的预算定额标准制定的设计预算成本计划，且一般情况下只确定责任总成本目标，这是指（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","控制性成本计划",false,{"key":16,"text":17,"correct":14},"B","竞争性成本计划",{"key":19,"text":20,"correct":21},"C","指导性成本计划",true,{"key":23,"text":24,"correct":14},"D","实施性成本计划","本题考核的是施工成本计划的类型。 对于一个施工项目而言，其成本计划是一个不断深化的过程。在这一过程的不同阶段，形成深度和作用不同的成本计划，按其作用可分为三类。 因此，按照企业的预算定额标准制定的设计预算成本计划，且一般情况下只确定责任总成本目标，是指导性成本计划。 综上所述，正确选项为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]