[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140933":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140933,799,1,"单选题","施工企业在工程投标阶段编制的估算成本计划是一种（ ）成本计划。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","指导性",false,{"key":16,"text":17,"correct":14},"B","实施性",{"key":19,"text":20,"correct":14},"C","作业性",{"key":22,"text":23,"correct":24},"D","竞争性",true,"本题主要考查成本计划的类型。 施工成本计划按其作用可分为三类，如图所示： 所以施工企业在工程投标阶段编制的估算成本计划是一种竞争性成本计划。 综上所述，本题正确选项为D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]