[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140927":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140927,799,2,"多选题","根据《建筑工程施工合同（示范文本）》（GF—2013—0201），可以顺延工期的情况有（ ）。( 2015真题 )",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发包人比计划开工日晚5天下达开工通知",false,{"key":16,"text":17,"correct":18},"B","发包人未按合同约定提供施工现场",true,{"key":20,"text":21,"correct":18},"C","发包人提供的测量基准点存在错误",{"key":23,"text":24,"correct":18},"D","监理未按合同约定发出指示、批准文件",{"key":26,"text":27,"correct":14},"E","分包商或供货商延误","BCD","本题考查的是施工承包合同的内容。选项A，正确的表述应为“发包人未能在计划开工日期之日起7天内同意下达开工通知的”；选项E属于承包方的原因，不能索赔工期。@##",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]