[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140911":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140911,799,1,"单选题","施工成本管理的最根本、最重要的基础工作是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","明确成本管理的指导思想",false,{"key":16,"text":17,"correct":14},"B","建立企业内部施工定额",{"key":19,"text":20,"correct":14},"C","科学设计施工成本核算账册",{"key":22,"text":23,"correct":24},"D","建立成本管理责任体系",true,"本题主要考查施工成本管理的基础工作内容。 施工成本管理的基础工作内容是多方面的，建立成本管理责任体系的是其中最根本、最重要的基础工作，涉及成本管理的一系列组织制度、工作程序、业务标准和责任制度的建立。 综上所述，本题正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]