[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140896":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140896,799,1,"单选题","施工成本核算要求的归集“三同步”是指（ ）的取值范围应当一致。( 2015真题 )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","形象进度、产值统计、实际成本",true,{"key":16,"text":17,"correct":18},"B","成本预测、成本计划、成本分析",false,{"key":20,"text":21,"correct":18},"C","目标成本、预算成本、实际成本",{"key":23,"text":24,"correct":18},"D","人工成本、材料成本、机械成本","本题考查的是施工成本核算。形象进度、产值统计、实际成本归集“三同步”，即三者的取值范围应是一致的。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]