[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140895":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140895,799,1,"单选题","竣工工程进行现场成本、完全成本核算的目的是分别考核（）。2018真题",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","企业经营效益、企业社会效益",false,{"key":16,"text":17,"correct":14},"B","项目管理绩效、项目管理责任",{"key":19,"text":20,"correct":14},"C","项目管理责任、企业经营效益",{"key":22,"text":23,"correct":24},"D","项目管理绩效、企业经营效益",true,"本题考查的是成本管理的任务。对竣工工程的成本核算，应区分为竣工工程现场成本和竣工工程完全成本，分别由项目管理机构和企业财务部门进行核算分析，其目的在于分别考核项目管理绩效和企业经营效益。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]