[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140893":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140893,799,1,"单选题","建设工程项目施工成本管理涉及的时间范围是（ ）。 2016",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","从工程投标报价开始至项目保证金返还为止",true,{"key":16,"text":17,"correct":18},"B","从施工图预算开始至项目运用为止",false,{"key":20,"text":21,"correct":18},"C","从工程投标报价开始至项目竣工结算完成为止",{"key":23,"text":24,"correct":18},"D","从施工准备开始至项目竣工结算完成为止","本题考查的是建设工程项目施工成本控制。建设工程项目施工成本管理应从工程投标报价开始，直至项目保证金返还为止，贯穿于项目实施的全过程。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]