[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140891":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1140891,799,1,"单选题","作为施工企业全面成本管理的重要环节，施工项目成本控制应贯穿于（ ）的全过程。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","从项目策划开始到项目开始运营",false,{"key":16,"text":17,"correct":14},"B","从项目设计开始到项目开始运营",{"key":19,"text":20,"correct":21},"C","从项目投标开始到项目竣工验收",true,{"key":23,"text":24,"correct":14},"D","从项目施工开始到项目竣工验收","本题考核的是建设工程项目施工成本管理的任务。 建设工程项目施工成本管理从工程投标报价开始，直至竣工结算完成为止，贯穿于项目实施的全过程，它是企业成本管理的重要环节。 综上所述，本题正确答案为C。 *新版已经改成到项目保证金返还为止",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]