[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140888":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140888,799,2,"多选题","施工成本构成的内容包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","人工费",true,{"key":16,"text":17,"correct":14},"B","材料费",{"key":19,"text":20,"correct":21},"C","利润",false,{"key":23,"text":24,"correct":21},"D","税金",{"key":26,"text":27,"correct":21},"E","设备及工器具购置费","AB","本题主要考查施工成本构成。 施工成本如下图所示： 本题中，施工成本构成的内容应包括人工费和材料费。 综上所述，本题正确选项是AB项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]