[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140886":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140886,799,2,"多选题","建设工程项目施工成本偏差分为（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","累计成本偏差",true,{"key":16,"text":17,"correct":14},"B","局部成本偏差",{"key":19,"text":20,"correct":21},"C","单项工程成本偏差",false,{"key":23,"text":24,"correct":21},"D","专项成本偏差",{"key":26,"text":27,"correct":21},"E","单位工程成本偏差","AB","本题主要考查对施工成本偏差的理解。 成本偏差分为局部成本偏差和累计成本偏差。局部成本偏差包括项目的月度（或周、天等）核算成本偏差、专业核算成本偏差以及分部分项作业成本偏差等；累计成本偏差是指已完工程在某一时间点上实际总成本与相应的计划总成本的差异。 综上所述，本题正确答案为AB。 *",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]