[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140883":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140883,799,1,"单选题","项目经理部对竣工工程成本核算的目的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","考核项目管理绩效",true,{"key":16,"text":17,"correct":18},"B","寻求进一步降低成本的途径",false,{"key":20,"text":21,"correct":18},"C","考核企业经营效益",{"key":23,"text":24,"correct":18},"D","分析成本偏差的原因","本题主要考查竣工工程成本的核算。 对竣工工程成本核算，应区分为竣工工程现场成本和竣工工程完全成本，分别由项目经理部和企业财务部门进行核算，目的分别在于考核项目管理绩效和企业经营效益。因此，项目经理部对竣工工程成本核算的目的是考核项目管理绩效。 综上，本题正确答案应为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]