[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140882":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1140882,799,1,"单选题","施工成本管理任务中，（ ）是建立施工项目成本管理责任制、开展成本控制和核算的基础。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工成本预测",false,{"key":16,"text":17,"correct":14},"B","施工成本分析",{"key":19,"text":20,"correct":21},"C","施工成本计划",true,{"key":23,"text":24,"correct":14},"D","施工成本考核","本题主要考查建设工程项目施工成本控制。 施工成本计划是以货币形式编制施工项目在计划期内的生产费用、成本水平、成本降低率以及为降低成本所采取的主要措施和规划的书面方案，它是建立施工项目成本管理责任制、开展成本控制和核算的基础，它是该项目降低成本的指导文件，是设立目标成本的依据。 综上所述，本题正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]