[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140878":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1140878,799,1,"单选题","建设工程项目施工成本管理的任务和环节包括：①成本分析；②成本控制；③成本考核；④成本预测；⑤成本核算；⑥成本计划。其正确的顺序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","⑥-④-②-①-⑤-③",false,{"key":16,"text":17,"correct":18},"B","④-⑥-②-⑤-①-③",true,{"key":20,"text":21,"correct":14},"C","④-①-⑥-②-⑤-③",{"key":23,"text":24,"correct":14},"D","①-④-⑥-②-③-⑤","本题主要考查对建设工程项目施工成本管理的理解。 施工成本管理的任务和环节主要包括：1、施工成本预测；2、施工成本计划；3、施工成本控制；4、施工成本核算；5、施工成本分析；6、施工成本考核。具体见下表： 综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]